Constructions Standards Checklists
TILE SHOWER STALL – LIQUID MEMBRANE APPROACH
SHOWERS AND TUBS A. All shower units must have a continuous, integral tiling flange that is a minimum of 1" high. No cracked or damaged flanges are permitted. B. 2x6 blocking is installed at perimeter of shower at flange height - bottom edge of blocking should be approximately 1" below top of tiling flange. C. 4" butyl based self-adhered flashing is used to seal the pan flange to the 2x6 blocking - Use "7 step approach" with 6" pieces of flashing in front and back corners and individual pieces of flashing between corners. D. Shower backerboard is installed with a factory
edge down towards shower unit and held just above top of tiling flange -backerboard should extend beyond surround area so that the joint between backer board and drywall does not align with edge of tile. E. Seal all corners, joints, and any fasteners that break the surface with C920 Class 25 sealant. F. Apply liquid applied waterproof membrane to all seams. Follow manufacturer's installation specifcations - two coats are required to achieve required membrane thickness. G. Leave a minimum 1/8" gap between tile and shower unit for sealant. H. Pan weeps were open and clear of grout and sealant. I. Do not grout the corners or transition to the shower pan – seal using C920 Class 25 sealant. J. Any shower seats shall have a continuous waterproofng membrane over them.
CONSTRUCTION STANDARDS CHECKLISTS | Showers & Tubs | 47
Made with FlippingBook Learn more on our blog