BLOCK WALL – GENERAL
DRAINAGE PLANE A. Block seat has been cast into foundation. B. At roof to wall intersections there is a spacer to keep the trusses from resting on the CMU. C. Butyl tape was installed at the concrete masonry unit (CMU) block wall to wood frame construction. D. Housewrap is properly installed and overlaps the weep screed at the CMU block wall to wood frame transition by at least 1". E. Penetration locations including at the base of wall and utility penetrations have been mortar packed and sealed with sealant where necessary. F. Lath installed at penetrations where necessary to ensure proper stucco adhesion.