Constructions Standards Checklists

BLOCK WALL – GENERAL

DRAINAGE PLANE  A. Block seat has been cast into foundation.  B. At roof to wall intersections there is a spacer to keep the trusses from resting on the CMU.  C. Butyl tape was installed at the concrete masonry unit (CMU) block wall to wood frame construction.  D. Housewrap is properly installed and overlaps the weep screed at the CMU block wall to wood frame transition by at least 1".  E. Penetration locations including at the base of wall and utility penetrations have been mortar packed and sealed with sealant where necessary.  F. Lath installed at penetrations where necessary to ensure proper stucco adhesion.

CONSTRUCTION STANDARDS CHECKLISTS | Drainage Plane | 37